Case StudyFLOW CONTROLRefinery
PROJECT REF-24-01202414 weeks · RFQ to handover
// PENGERANG, JOHOR //

Refinery turnaround valve supply

180 critical-service valves engineered, supplied, installed and commissioned inside a 21-day shutdown window — with sour-service materials on the hot end and zero punch items at handover.

refinery-night
Pengerang Integrated Complex
Crane / XOMOX
CLIENT
Confidential · Major Refinery
SCOPE
180 valves · supply + install
DURATION
14 weeks · RFQ to handover
DELIVERED
On schedule · zero defects
// 01 //
The brief

A 21-day hydroprocessing turnaround left no margin for re-work. The operator needed sleeve plug and high-performance butterfly valves — fully certified, sour-service rated where the process demanded it — and a single partner who could carry the scope from spec walkdown all the way through field commissioning.

// THE CHALLENGE //
01

Replace 180 valves across utilities and hot-end process inside a fixed 21-day shutdown — with NACE MR0175 sour-service materials on critical isolation and zero room for slippage on long-lead items.

// THE APPROACH //
02

Engineering-led: a 3-day walkdown to verify every line, a single OEM-direct proposal from Crane / XOMOX, and pre-staging at the plant warehouse 4 weeks before Day 1 of the shutdown.

// THE OUTCOME //
03

All 180 valves delivered, installed and commissioned on schedule. Refinery returned to full production 3 days ahead of the original turnaround plan. Zero punch items related to Cosmos scope.

// 02 — SCOPE BREAKDOWN //

What we
delivered

A single-source supply, with Cosmos engineers running the spec walkdown, OEM-direct procurement, pre-staging, and field commissioning.

180
Valves supplied & installed
14
Weeks RFQ to handover
100%
Factory-test certified
0
Punch items at handover
01

Line-by-line walkdown

3-day site survey verifying spec, pressure class, materials and face-to-face on every position in scope.

ENGINEERING
02

OEM-direct supply

Single engineering proposal sourced manufacturer-direct from Crane / XOMOX — no broker chain.

PROCUREMENT
03

Sour-service materials

NACE MR0175-compliant body and trim materials specified on every critical isolation valve.

MATERIALS
04

Pre-staging at site

All units delivered to the plant warehouse 4 weeks before shutdown, with full traceability documents.

LOGISTICS
05

Field installation

Cosmos field crew on-site for the full 21-day shutdown window, supporting client fitters and QC.

FIELD
06

Loop commissioning

Actuator stroke, limit switch and positioner commissioning on the 38 actuated positions in scope.

COMMISSIONING
// 03 — ON-SITE //

From the field

03 / 03 IMAGES
// 04 — BILL OF MATERIALS //

Equipment
supplied

All units sourced manufacturer-direct, tested at the factory and re-certified on arrival at the plant warehouse. Sour-service materials on critical isolation lines.

View product range
Product
OEM
Service
Qty
Sleeve Plug Valve
PB / FS series · ANSI 150–600
Crane / XOMOX
Hot-end isolation
96
High-Performance Butterfly Valve
Metal-seated · ANSI 150–300
Crane / XOMOX
Utilities & cooling
58
Lined Plug Valve (PFA)
Severe-service · DN50–DN200
Crane / XOMOX
Aggressive chemical
14
Pneumatic Actuator Package
Spring-return · Class IP66M
Crane Resistoflex
Actuated isolation
38
Total units
206
// 05 — PROJECT TIMELINE //

14 weeks,
RFQ to handover

Week 0
RFQ received · spec walkdown
Cosmos lead engineer on-site for 3 days with the reliability and maintenance teams.
Week 2
Engineering proposal · spec freeze
Single document covering all 180 positions, materials, certs and lead times.
Week 6
OEM-direct purchase order placed
Manufacturer factory slots locked for sour-service material runs.
Week 10
First lot delivered to plant warehouse
Pre-staging begins 4 weeks ahead of the shutdown window — full traceability.
Week 12
Field install · loop commissioning
21-day shutdown window — Cosmos field crew on-site the full duration.
Week 14
Punch-out · handover · documentation
Zero punch items related to Cosmos scope. Refinery restart 3 days early.
// RESULTS //
3 days
Ahead of turnaround schedule
0
Punch items at handover
180/180
Units test-certified on delivery
100%
OEM-direct material traceability

Cosmos showed up to the walkdown with the engineer who wrote our proposal — not a salesperson. That continuity from RFQ through commissioning is what made the turnaround land on schedule.

RM
Reliability Manager
Hydroprocessing Refinery · Pengerang
Industrial plant engineering

Ready to spec us
into your next project?

From RFQ to installation, our engineering team is ready to help you maximize plant integrity and uptime.